Multi-phased replacement of (5) non-compliant existing air handlers at the Ukiah Valley Medical Center. Each phase required installation of a new air handler and associated ductwork and roof supports. Once each new air handler was started, tested and commissioned, the non-compliant air handlers were decommissioned and the new air handlers cutover to the new ductwork and existing infrastructure. Re-balancing the existing system to comply with new airflow requirements and the associated upgrades was completed post cutover to achieve enhanced air flows.
Work was completed in an occupied (OSHPD 1) hospital facility with no disruption to patient care.